The awards meeting counts a promising bid beside signed jobs, while finance’s remaining-work total excludes it. Construction backlog measures work already under contract that has not been performed, according to Associated Builders and Contractors’ June 2023 methodology. Keep unsigned pipeline separate, then reconcile remaining contract value from one cutoff to the next.
Use ending backlog = opening backlog + accepted new contract value + accepted changes - performed contract value - authorized cancellations under one declared reporting basis. This is a movement bridge, not a choice of revenue-recognition policy. The controller must approve which source amounts represent performed work and which contract statuses enter the calculation (including how partial authorizations are handled).
Contract administration verifies the accepted scope
Start with the signed contract or other evidence accepted under your company’s authorization policy. Record the company, customer, contract ID, project ID, currency, effective date, and value covered by that authorization. A project name in the sales list is insufficient when several contracts or phases share the name. Contract administration owns the evidence linking an award to the work the company has agreed to perform.
Separate bids, verbal expectations, letters awaiting required conditions, and disputed claims from the accepted baseline. If a limited authorization covers only an early phase, retain its authorized scope rather than inserting the anticipated full project value. Assign an owner to unresolved awards so the meeting can discuss them without making them indistinguishable from contracted work.
Build the opening position from the prior approved snapshot, not a fresh export that already incorporates later changes. At contract level, retain accepted contract value and the approved measure of work performed to date. Their difference establishes the remaining-work starting point under that basis. A negative balance needs review rather than being forced to zero, because it can indicate duplicate progress, an omitted change, or inconsistent scope.
Project managers link changes and cancellations to contracts
The project manager supplies the accepted change reference, amount, effective date, and affected contract. Contract administration confirms its authority, and finance maps it into the reporting period. Procore’s prime-contract column documentation distinguishes approved, pending, and draft changes and includes approved changes in revised contract amount. Preserve comparable distinctions in your own data.
Choose either a revised contract total or original value plus accepted changes as the starting calculation. Adding a separate change register to a revised total that already includes those changes counts the same scope twice. Match change identifiers before summing, and keep pending amounts visible beside the accepted baseline rather than treating a proposed amount as an approved addition.
Record a cancellation or scope reduction when the authorized decision applies, with its supporting reference. A delayed start is not automatically a cancellation. Preserve the difference between remaining contracted work and the operations team’s expectation of when it will begin. Disputed or conditional situations stay assigned for review instead of being resolved by a spreadsheet status rule.
The controller approves performed work at a common cutoff
Ask each project manager for progress evidence and have the controller map it to the contract-value basis used in backlog. Apply one cutoff to the opening balance, accepted changes, and work performed during the period. Raw job costs do not equal performed contract value, and an invoice date does not establish when work was performed. Keep the mapping and its approval with the result.
The construction WIP report connects approved contract values, progress, earned revenue, and billings. Reconcile shared inputs with that schedule where the reporting bases agree, and explain differences where they do not. A backlog calculation should not select cost-to-cost progress, billing totals, or a tax-accounting method for a contract.
Work already performed leaves remaining-work backlog even if the owner has not yet paid for it. Unbilled performed work, receivables, and retainage on completed work belong in billing and collection views. A customer deposit can arrive before work is performed, so receiving cash does not by itself reduce this backlog. Keep physical progress, billing, and cash events separate.
Finance reconciles the opening and closing snapshots
Consider a hypothetical US-dollar portfolio for October 2026. The opening snapshot contains $1,200,000 of remaining accepted work. New accepted awards add $700,000, accepted changes add $100,000, and authorized cancellations remove $50,000. Assume the controller has approved $400,000 as the period’s performed contract value on the same basis. No currency changes, acquisitions, or other adjustments enter this example.
| Bridge item | Movement | Evidence owner |
|---|---|---|
| Opening backlog, October 1 | $1,200,000 | Finance: prior approved snapshot |
| New accepted awards | +$700,000 | Contract administration: accepted scope |
| Accepted contract changes | +$100,000 | Project manager: approved change references |
| Performed contract value | -$400,000 | Controller: approved progress mapping |
| Authorized cancellations | -$50,000 | Contract administration: effective reductions |
| Ending backlog, October 31 | $1,550,000 | Finance: contract-level reconciliation |
The arithmetic is $1,200,000 + $700,000 + $100,000 - $400,000 - $50,000 = $1,550,000. Run the bridge by contract before summing the portfolio. A matching company total can conceal an omitted award offset by duplicated remaining work on another job. Investigate any difference between the movement bridge and the closing contract-level calculation instead of posting an unexplained balancing amount.
Retain source extraction times, effective dates, and the snapshot approval. If a late change or progress correction belongs to the earlier period, finance decides whether to revise that snapshot or show an identified adjustment in the next bridge. Keep the old and revised versions so reviewers can explain why a previously issued backlog amount changed.
Finance labels revenue-based months with the prior fiscal year
ABC’s methodology converts dollars using backlog months = current month’s backlog / prior fiscal year revenue × 12. Its survey covers ABC members in nonresidential construction, with results separated by firm size, geography, and segment. The measure scales contracted work by a past revenue pace; it does not assign crews or establish a company target.
For the example, assume the same company and reporting scope had $3,100,000 of revenue in its prior fiscal year. The calculation is $1,550,000 / $3,100,000 × 12 = 6 months. Label the denominator with that fiscal year and retain its source. A different revenue period or company scope produces a different measure, even when the remaining contracts have not changed.
Six revenue-based months does not mean the company can finish every remaining contract six calendar months from the cutoff. Work can be delayed, concentrated in a trade, or spread across different start dates. If prior-year revenue is zero, the ratio is undefined. If it reflects a different business scope, show that limitation rather than presenting the result as comparable coverage.
Operations and treasury review delivery and collection separately
Operations owns the delivery review: place remaining work against expected start dates, required trades, available crews, and constraints. An accepted award may add backlog while needing a scarce crew in a period already committed elsewhere. Review expected margin from the current cost outlook as a separate question; a contract-value total alone does not establish the cost of delivering it.
Supplier and subcontract commitments are cost obligations, not additional customer backlog. The committed costs article separates revised agreements, matched actuals, and open balances. Keep those costs available to the delivery review without adding them to the customer contract value or subtracting them as if they were performed revenue.
Treasury owns the collection review, using billing milestones, payment terms, retainage release conditions, and expected receipt dates. The construction cash flow forecast develops that dated view. Backlog is an input to the discussion of future work; it does not establish available cash, a collection date, or the funding needed before the owner pays.
Inspect the records behind a remaining-work question
Start with an available source and examine which contracts and progress records support the answer.
Permute: match contract and project identities for review
Permute sells connected business data and custom applications. We can scope workflows that match supplied contract and project records with supported accounting sources such as QuickBooks. The matching retains company-scoped contract keys and source references, so similarly named jobs do not become one project without an accepted link.
We can apply the controller’s declared status and progress mappings in a reusable calculation and present exceptions in an App. A controller could inspect a backlog movement, follow it to the contract or progress evidence, and identify unresolved matches. Current user permissions and the App’s source grants control which records the reviewer can access.
Keep accounting judgment and scheduling authority with owners
This workflow reads permitted records for analysis. We do not decide whether an award is binding, choose revenue-recognition treatment, approve a cancellation, or commit crews to a schedule. We are not a forecasting engine; the calculation supplies governed inputs for the team’s planning. Missing approval or identity evidence remains an exception until its owner resolves it.
Close the meeting with a reconciled remaining-work amount
Construction backlog should reconcile accepted work remaining, with unsigned pipeline shown separately. The period bridge explains how awards, changes, performed work, and cancellations move that amount. Revenue-based months put it against a declared prior-year pace, while delivery and collection need their own reviews. Keep the contract evidence and reporting cutoff with the result so the next meeting can explain movement rather than redefine the total.
Scope a repeatable contract-to-progress review
Bring an awards register, the approved progress basis, and a prior backlog snapshot to review the missing links.
Questions about remaining contracted work
How much backlog should a company carry?
Compare the remaining work with your delivery constraints, expected costs, and collection timing. A survey reading for other firms cannot establish your company’s appropriate level. A larger dollar amount can still concentrate work in a period or trade where capacity is unavailable.
Does billing work remove it from backlog?
Use the approved performed-work measure rather than billing alone. A billing event can lead or lag performance, while a receipt has its own timing. Keep the invoice and payment references available for reconciliation without substituting them for work performed.
Should a delayed job disappear from the total?
A delay alone does not establish that the remaining contract was canceled. Preserve the accepted amount and flag the expected-start uncertainty for the operations review. Contract administration and finance should determine how an authorized scope reduction or other change affects the reported balance.